CONCRETING

Site preparation and concreting.

If the building is larger than an average garage, a soil test should be conducted to determine the suitability of the site and aid the design of footings. A good building site should be level and clear of large rocks or old stumps. Vegetation must be removed and the site formed into a slight crest so water runs away from the construction area in all directions. It is much easier and more economical to do this before any assembly work begins.

In addition to a slab or floor, large buildings require concrete footings below each wall column. These may be mass footings (concrete pads) or bored piers. They require steel reinforcing in the form of rods and/or prefabricated cages. Consult the footing plan provided with the building before commencing any work.

This page is intended as a general guide for placing concrete slabs, but similar comments apply to placing concrete footings. See the assembly pages linked above or below for erecting steelwork and attaching cladding.

Click on the image to see a larger photo.


imagea/sb01s.jpg

imagea/sb02s.jpg
SB01. Clear all vegetation and rubbish before levelling the site. Set out the location of the slab and holding down devices by making profiles to hold string lines.
SB02. Excavate for edge beam and fill area beneath the slab to required levels. Note that extra trench beams may be required for slabs to support heavy machinery or for residential use.
imagea/sb03s.jpg

imagea/sb04s.jpg
SB03. Clean out trenches to required depth and level the fill. Note the battered (chamfered) edges of the fill so there are no sharp corners under the slab to create future cracking points.
SB04. Tape edges of moisture membrane so no soil contacts the concrete. Place reinforcing fabric and tie together being careful not to penetrate the plastic. Position holding down anchors.
imagea/sb05s.jpg

imagea/sb06s.jpg
SB05. Spread concrete evenly, working it into all corners so there are no voids. Care needs to be taken so the reinforcing is kept at least 50mm above the membrane and that it is not penetrated.
SB06. Do not try to pour and finish the slab in one go. Place a part at a time and screed it off as you go. When the first section is ready, trowling may begin while placement continues.
imagea/sb07s.jpg

imagea/sb08s.jpg
SB07. Screeding removes excess concrete while levelling the slab. Trowling brings air bubbles to the surface and must be carried out before the concrete sets.
SB08. Concrete is said to be "green" before it hardens properly. Although it looks hard, it can easily be damaged and should be protected and kept moist while curing.

Note that the above information is only intended as a brief outline of the basic steps required to place a concrete slab. Site preparation, concreting and erection of steelwork are best done by qualified and licensed tradespeople. Contact your nearest Ranbuild Team who can arrange an experienced building erector for you.

All construction sites and shed erectors should comply with the occupational health and safety requirements and your local Workcover authority. The National Occupational Health and Safety site is a good source of information and includes links to Workcover and other associated sites.

For information on concreting, including materials, mixing and placing, go to the Cement Concrete & Aggregates Australia web site where you will find a comprehensive list of services and advice.

For information on erecting Ranbuild rural, commercial or industrial sheds and buildings, go to the Shed Assembly page where you will see photos of larger buildings being erected.

For information on erecting Ranbuild garages, barns and Big_G buildings, go to the Garage Assembly page where you will see step-by-step photos of Deluxe building being erected.

images/line1.gif

- Return to top of Page -

[ Home ][ Profile ][ Products ][ Colours ][ Contact ][ Sitemap ][ News ][ Links ]

COLORBOND®, LYSAGHT® and ZINCALUME® are registered trade marks of BlueScope Steel Limited.
Ranbuild® and Covermaster® are registered trade marks of Lysaght Building Solutions Pty Ltd.
Copyright 2005: Lysaght Building Solutions Pty Ltd, trading as Ranbuild.

This page last updated 10/02/2006.